2014
Access Midstream Partners
Mudhole Phase 4
Blasted approximately .75 miles of 6" pipeline for a 1.1 mile project
Talisman Energy, Inc.
Mountain Run to River Road
Current project 2.56 miles of 6" pipeline
Sunoco Pipeline, LP - Marinier East
Current project 21 miles of 12" pipeline
Williams Partners, LP - Hickory & Hartley Gathering
Current project 4 miles of 12" pipeline
2013
PVR Partners, L.P.
Abel Wistar Gathering
Blasted approximately .2 miles (Winch Hill Only) for 16" pipeline of a 9 mile project
PVR Partners, L.P.
Meshoppen
Blasted approximately 2.09 miles of 16" pipeline for a 6 mile project
PVR Partners, L.P.
Trout Run
Blasted approximately 1.89 miles of 16" pipeline for a 5 mile project
Access Midstream Partners
Forkston-Wootten
Blasted approximately .36 miles of 20" pipeline for a 3.7 mile project
Access Midstream Partners
Mudhole
Blasted approximately 1.33 miles of 12" pipeline for a 4 mile project
Shell Appalachia
Pad Spur
Blasted approximately .3 miles of 12" pipeline for a .4 mile project
Dominion Transmission, Inc.
Line TL 465
Drilled for expanding mortar usage
Williams Partners, LP
Millard Gathering
Blasted approximately .49 miles of 16" pipeline for a 3.6 mile project
Access Midstream Partners
Vista Gathering
Blasted approximately 1.47 miles of 8, 12, 16" pipeline of a 6.6 mile project
Access Midstream Partners
Connell Gathering
Blasted approximately 3.09 miles of 12, 16" pipeline for a 11.4 mile project
2012
WPX Energy, Inc.
Kass Robinson Lateral
Blasted approximately .71 miles of 8" pipeline for a 1.2 mile project
Shell Appalachia
Guillaume Spur
Blasted approximately .91 miles of 8, 10, 12" pipeline for a 1.7 mile project
Shell Appalachia
Marshall Spur
Blasted approximately .78 miles of 8, 10, 12" pipeline for a 1.4 mile project
Shell Appalachia
Texas Creek Pink
Blasted approximately 2.33 miles of 12, 16, 20" pipeline for a 10.9mile project
National Fuel Gas Supply Corporation
Trout Run
Blasted approximately .12 miles of 8, 12" pipeline for a 1.7 mile project
PVR Partners, L.P.
Gathering Phase III
Blasted bore pit only
PVR Partners, L.P.
Myers to Marquardt
Blasted approximately 4.59 miles of 16" pipeline for a 5.5 mile project
Kinder Morgan, Inc.
El Paso 315 Line
Blasted approximately .52 miles of 30" pipeline for a 6.8 mile project
PVR Partners, L.P.
Harris - Postell
Blasted approximately .28 miles of 12" pipeline for a 5.1 mile project
Anadarko Petroleum Corporation
Warrensville Lateral
Blasted bore pit only
Chesapeake Midstream Partners, L.P.
Cranrun to Petty
Blasted approximately 1.11 miles of 16" pipeline for a 4.7 mile project
Chief Gathering, LLC
Garrison Lateral
Blasted approximately .23 miles of 8" pipeline for a .5 mile project
WPX Energy, Inc.
Line 418
Blasted approximately 1.51 miles of 12" pipeline for a 3.5 mile project
WPX Energy, Inc.
Northeast Ph II
Blasted approximately 1.24 miles of 12" pipeline for a 2.8 mile project
WPX Energy, Inc.
Snake Creek
Blasted approximately 1.9 miles of 16" pipeline for a 9.5 mile project
2011
Chesapeake Midstream Partners, L.P.
Moon Project
Blasted approximately .6 miles of 12" pipeline for a .7 mile project
Chief Gathering, LLC
Phelps to Kerr Project
Blasted approximately 2.46 miles of 8" pipeline for a 2.8 mile project
Chief Gathering, LLC
Polovitch to Wilson
Blasted approximately 5.64 miles of 12" pipeline for a 9.5 mile project
Pennsylvania General Energy Company, LLC
Honniasont Phase I
Blasted approximately .08 miles of 24" pipeline for a 11 mile project
PVR Partners, L.P.
Gathering Phase II
Blasted approximately 5.37 miles of 30" pipeline for a 14.5 mile project
Spectra Energy
Marietta Discharge
Blasted approximately 2.9 miles of 30" & 36" pipeline for a 28 mile project
Laser Northeast Gathering, LLC
Montrose Lateral
Blasted approximately .92 miles of 12" pipeline for a 6.7 mile project
Shell Appalachia
Palmer-Castle
Blasted approximately .95 miles of 6" pipeline for a 2.9 mile project
Shell Appalachia
TC Green Dry
Blasted approximately .7 miles of 6" pipeline for a 3.3 mile project
2010
Chief Gathering, LLC
Booth Hazlak Gathering
Blasted approximately 3.12 miles of 16" pipeline for a 9.7 mile project
Chief Gathering, LLC
Fulmer Gathering
Blasted approximately 1.86 miles of 12" pipeline for a 2.8 mile project
Chief Gathering, LLC
King Gathering
Blasted approximately 2.99 miles of 16" pipeline for a 3.9 mile project
Chief Gathering, LLC
Polovitch Gathering
Blasted approximately .12 miles of 8" pipeline for a 1.0 mile project
Talisman Energy, Inc.
Bense to Eick
Blasted approximately .79 miles of 12" pipeline for a 6.7 mile project
PVR Partners, L.P.
Gathering Phase I
Blasted approximately .42 miles of 30" pipeline for a 13.5 mile project
Chief Gathering, LLC
Myers Gathering
Blasted approximately 1.09 miles of 12" pipeline for a 2.7 mile project
Shell Appalachia
Foti-Clegg
Blasted approximately .27 miles of 6" pipeline for a 1.2 mile project
2009
East Resources, Inc.
Troy Gathering
Blasted approximately 2.89 miles of 12" pipeline for a 17 mile project